A-04 · ProjectsR-08 · Single-family house
Ceramic block house: floor slab and shell
A cast-in-place floor slab over the ground floor – rebar in two directions, pumped concrete, floating – and two months later the building with a roof.
- Period
- 11.10.2022 – 25.12.2022
- Entries
- 02
- Photos
- 07
Scope on the diagramR-08
- FoundationsFoundations: not documented
- Reinforced concreteReinforced concrete: not documented
- WallsWalls: visible as finished
- Floor slabFloor slab: KMB work in the photos
- Roof structureRoof structure: not documented
- RoofRoof: visible as finished
- KMB work in the photos
- Visible as finished
- Not documented
Site diary
2 entries · dates from company posts · 76 days in photos
- Entry 01/0211.102022 · day 1
Floor slab over the ground floor
Two layers of rebar mesh on the formwork, level checked with a levelling instrument, concrete placed by pump and power-floated.
- Entry 02/0225.122022 · day 76
Shell with a roof
Attic walls of ceramic hollow blocks, roof covered, roof windows installed.
- Building
- Single-family house
- Location
- Period in photos
- 11.10.2022 – 25.12.2022
- KMB work in the photos
- floor slab
- Technology
- Ceramic hollow blocks
- Cast-in-place floor slab
- Pumped concrete
- Photo source
- KMB Konstrukcje, posts from the site
- Sheet
- R-08