A-04 · ProjectsR-03 · Single-family house

House by the forest: from setting out to walls

Setting out with batter boards and string lines, excavation, strip footings poured by pump in the first snow, and after the winter, ground-floor walls of sand-lime blocks.

Period
17.11.2021 – 28.02.2022
Entries
03
Photos
12

Scope on the diagramR-03

  1. FoundationsFoundations: KMB work in the photos
  2. Reinforced concreteReinforced concrete: not documented
  3. WallsWalls: KMB work in the photos
  4. Floor slabFloor slab: not documented
  5. Roof structureRoof structure: not documented
  6. RoofRoof: not documented
  • KMB work in the photos
  • Not documented

Site diary

3 entries · dates from company posts · 104 days in photos

  1. Entry 01/0317.112021 · day 1

    Setting out and excavation

    Batter boards with string lines around the building outline, a mini excavator digging trenches for the strip footings.

  2. Entry 02/0330.112021 · day 14

    Footings poured by pump

    Rebar in the trenches, concrete placed by pump, spread and compacted – despite the snow.

  3. Entry 03/0328.022022 · day 104

    Ground-floor walls

    The first course of blocks levelled on mortar, then external and partition walls of sand-lime blocks, with lintels over the openings.

Building
Single-family house
Period in photos
17.11.2021 – 28.02.2022
KMB work in the photos
foundations, walls
Technology
  • Reinforced concrete strip footings
  • Pumped concrete
  • Sand-lime blocks
Photo source
KMB Konstrukcje, posts from the site