Reinforced concrete basement level

A full cast-in-place concrete cycle: excavation, blinding concrete, waterproofing, base slab, walls in system formwork and the floor slab. From the first to the last photo – just over a month.

Period
07.09.2021 – 08.10.2021
Entries
05
Photos
24

Scope on the diagramR-02

  1. FoundationsFoundations: KMB work in the photos
  2. Reinforced concreteReinforced concrete: KMB work in the photos
  3. WallsWalls: not documented
  4. Floor slabFloor slab: KMB work in the photos
  5. Roof structureRoof structure: not documented
  6. RoofRoof: not documented
  • KMB work in the photos
  • Not documented

Site diary

5 entries · dates from company posts · 32 days in photos

  1. Entry 01/0507.092021 · day 1

    Excavation

    A mini excavator and excavators on the plot, excavation for the basement level with sloped sides.

  2. Entry 02/0513.092021 · day 7

    Blinding concrete

    The bottom of the excavation poured and levelled with blinding concrete – a clean, even base for waterproofing and rebar.

  3. Entry 03/0520.092021 · day 14

    Waterproofing, rebar and base slab

    Bitumen membrane on the blinding concrete, slopes protected with plastic sheeting. Two layers of slab rebar mesh with starter bars left for the walls, then pouring and floating the slab.

  4. Entry 04/0501.102021 · day 25

    Walls in formwork

    Wall rebar and system formwork all around. After stripping the formwork – smooth reinforced concrete walls.

  5. Entry 05/0508.102021 · day 32

    Floor slab

    Slab formwork on props, rebar with a reinforced strip over the opening, concrete placed by pump and floated.

Building
Basement level
Period in photos
07.09.2021 – 08.10.2021
KMB work in the photos
foundations, reinforced concrete, floor slab
Technology
  • Cast-in-place reinforced concrete
  • System formwork
  • Bitumen membrane waterproofing
  • Pumped concrete