A-04 · ProjectsR-02 · Basement level
Reinforced concrete basement level
A full cast-in-place concrete cycle: excavation, blinding concrete, waterproofing, base slab, walls in system formwork and the floor slab. From the first to the last photo – just over a month.
- Period
- 07.09.2021 – 08.10.2021
- Entries
- 05
- Photos
- 24
Scope on the diagramR-02
- FoundationsFoundations: KMB work in the photos
- Reinforced concreteReinforced concrete: KMB work in the photos
- WallsWalls: not documented
- Floor slabFloor slab: KMB work in the photos
- Roof structureRoof structure: not documented
- RoofRoof: not documented
- KMB work in the photos
- Not documented
Site diary
5 entries · dates from company posts · 32 days in photos
- Entry 01/0507.092021 · day 1
Excavation
A mini excavator and excavators on the plot, excavation for the basement level with sloped sides.
- Entry 02/0513.092021 · day 7
Blinding concrete
The bottom of the excavation poured and levelled with blinding concrete – a clean, even base for waterproofing and rebar.
- Entry 03/0520.092021 · day 14
Waterproofing, rebar and base slab
Bitumen membrane on the blinding concrete, slopes protected with plastic sheeting. Two layers of slab rebar mesh with starter bars left for the walls, then pouring and floating the slab.
- Entry 04/0501.102021 · day 25
Walls in formwork
Wall rebar and system formwork all around. After stripping the formwork – smooth reinforced concrete walls.
- Entry 05/0508.102021 · day 32
Floor slab
Slab formwork on props, rebar with a reinforced strip over the opening, concrete placed by pump and floated.
- Building
- Basement level
- Location
- Period in photos
- 07.09.2021 – 08.10.2021
- KMB work in the photos
- foundations, reinforced concrete, floor slab
- Technology
- Cast-in-place reinforced concrete
- System formwork
- Bitumen membrane waterproofing
- Pumped concrete
- Photo source
- KMB Konstrukcje, posts from the site
- Sheet
- R-02