A-04 · ProjectsR-06 · Industrial hall · Kobierzyce
Walls in an industrial hall
Building tall walls of aerated concrete blocks inside a steel hall – working from scaffolding, with a reinforced concrete core column in the wall.
- Period
- 15.04.2022 – 19.04.2022
- Entries
- 02
- Photos
- 02
Scope on the diagramR-06
- FoundationsFoundations: not documented
- Reinforced concreteReinforced concrete: not documented
- WallsWalls: KMB work in the photos
- Floor slabFloor slab: not documented
- Roof structureRoof structure: not documented
- RoofRoof: not documented
- KMB work in the photos
- Not documented
Site diary
2 entries · dates from company posts · 5 days in photos
- Entry 01/0215.042022 · day 1
Bricklaying from scaffolding
The crew on two scaffolds builds the wall up to the height of the roof structure. The post was tagged with the location: Kobierzyce, LG Energy Solution Wrocław.
- Entry 02/0219.042022 · day 5
Wall up to the roof
The wall built up to the roof sheeting, pallets of aerated concrete blocks on the hall floor.
- Building
- Industrial hall
- Location
- Kobierzyce
- Period in photos
- 15.04.2022 – 19.04.2022
- KMB work in the photos
- walls
- Technology
- Aerated concrete blocks
- Reinforced concrete core column
- Scaffolding
- Photo source
- KMB Konstrukcje, posts from the site
- Sheet
- R-06